60 Pleasant Street, Bridgewater, NS, B4V 3X9
Tel: 902-543-4651 Fax: 902-543-6876
Emergency After Hours Tel: 902-543-5142

PAVEMENT RENEWAL -- SCHEDULE UPDATE

Share This!

PAVEMENT RENEWAL -- SCHEDULE UPDATE

As a result of rain stemming from Hurricane Teddy, there have been some adjustments to upcoming pavement renewal projects this week in Bridgewater. Motorists should plan their routes and allow for additional travel time accordingly.

The schedule is now as follows:

-- Milling/planing will take place on Empire Street on THURSDAY, SEPTEMBER 24, with paving to follow next week.

-- Milling/planing will take place on North Street, from the Town Line near Cookville to near the Petro Canada, on THURSDAY, SEPTEMBER 24, starting at apx. 7 a.m.

-- Also on Thursday, some additional milling/planing is scheduled for north King Street.

Paving of the roads will begin on Friday, September 25, and continue into midweek next week, weather pending.

For a map of work areas, please visit www.bridgewater.ca/roads.